United States › Grid › Interconnection queues › Texas
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in Texas (2021 requests) — page 4
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Third Coast BESS Battery storage · Third Coast BESS LLC |
103 MW | Agreement signed |
| Louisa Energy Storage Battery storage · VESI 49 LLC |
103 MW | Agreement signed |
| Seven Flags BESS Battery storage · Seven Flags BESS LLC |
103 MW | Agreement signed |
| Tierra Seca BESS Battery storage · Tierra Seca BESS LLC |
103 MW | Agreement signed |
| Bexar ESS Battery storage · Bexar ESS LLC |
103 MW | Agreement signed |
| Madrone Energy Storage Battery storage |
103 MW | Paused / redesign |
| Opuntia Solar SLF Solar + storage · Opuntia Solar, LLC |
102 MW | In study |
| Pisgah Ridge Solar 2 Solar + storage · Pisgah Ridge Solar 2, LLC |
102 MW | In study |
| Pisgah Ridge Storage 3 Solar + storage · Pisgah Ridge 3, LLC |
101 MW | In study |
| Las Moras Battery Battery storage · Las Moras Storage, LLC |
101 MW | In study |
| Vaca Storage Battery storage · Long Mount Storage, LLC |
101 MW | In study |
| Paradiso BESS Battery storage · VESI 13 |
101 MW | Agreement signed |
| Ringtail Ridge Storage Battery storage · KCE TX 26, LLC |
101 MW | In study |
| Hermes Solar Solar + storage · Bell 1 Solar, LLC |
100 MW | Agreement signed |
| Galvanic BESS Battery storage · CED Development Inc |
100 MW | In study |
| Backwater Storage Battery storage |
100 MW | Paused / redesign |
| Bordertown BESS Battery storage |
100 MW | Paused / redesign |
| Sunsetter BESS Battery storage · CED Development Inc. |
100 MW | In study |
| Leitrim 1 Solar Solar · Leitsol LLC |
98.4 MW | In study |
| Midpoint Solar Solar · Midpoint Solar, LLC |
98.3 MW | Agreement signed |
| Rocinante Solar Solar + storage · Brush Country Solar Project, LLC |
95.3 MW | Agreement signed |
| High Noon Storage Solar + storage · High Noon Solar Project, LLC |
94.0 MW | Agreement signed |
| Rosscommon Solar Solar · Roscsol, LLC |
91.0 MW | In study |
| Payne Battlecreek Solar · Gransolar Texas Ten, LLC |
85.0 MW | Agreement signed |
| Lupinus Storage 1 Solar + storage · Lupinus Solar, LLC |
84.0 MW | In study |
| Harper Energy Storage Battery storage · VESI 31 LLC |
82.4 MW | In study |
| Sunbelt Solar Solar + storage · Rose Hill Solar LLC |
81.5 MW | In study |
| Backwater Solar Solar |
80.0 MW | Paused / redesign |
| Gaia Storage Solar + storage · Gaia Solar, LLC |
78.8 MW | Agreement signed |
| Naduah Solar Solar · Gransolar Texas Fifteen, LLC |
77.6 MW | In study |
| Eagle Springs Solar Solar + storage · Eagle Springs Solar, LLC |
77.2 MW | Agreement signed |
| Eytcheson Ranches Solar Solar · Gransolar Texas Fourteen, LLC |
76.4 MW | In study |
| Photo BESS 1 Solar + storage · CED Development Inc. |
75.0 MW | In study |
| Umbra (Stockyard) BESS Battery storage |
73.0 MW | Paused / redesign |
| Venture Hill Storage Battery storage · KCE TX 24, LLC |
70.4 MW | In study |
| Blue Jay Solar II Solar · Blue Jay Solar I, LLC |
69.0 MW | Agreement signed |
| Starling Storage Solar + storage · Starling Storage, LLC |
63.6 MW | Agreement signed |
| Honeycomb Solar SLF Solar + storage · Honeycomb Solar, LLC |
61.4 MW | Agreement signed |
| Orange Grove BESS Solar + storage · Talitha Energy Project, LLC |
61.4 MW | Agreement signed |
| Bird Dog Energy Storage Battery storage · VESI 37 LLC |
60.4 MW | Agreement signed |
| Oriana BESS Solar + storage · Oriana Solar LLC |
60.3 MW | Agreement signed |
| Lampe Solar Solar · Gransolar Texas Seven LLC |
60.2 MW | In study |
| Whistle Solar Solar · Gransolar Texas Nineteen, LLC |
56.3 MW | In study |
| Bynum Solar Project Solar · Bynum Solar Project, LLC |
56.0 MW | Agreement signed |
| Fighting Jays Battery Battery storage |
53.2 MW | Paused / redesign |
| Sunbelt Storage Solar + storage · Rose Hill Solar LLC |
52.0 MW | In study |
| Steppe Reserve Storage Battery storage · KCE TX 25, LLC |
51.9 MW | In study |
| High Chaparral BESS 138kV Battery storage · High Chaparral Solar Project, LLC |
51.7 MW | Paused / redesign |
| Big River BESS Solar + storage · Rio Grande River Solar LLC |
51.3 MW | In study |
| Lumberjack Storage Battery storage · EDP Renewables North America LLC |
50.9 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)