🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Pisgah Ridge Storage 3

Pisgah Ridge Storage 3 is a 101 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Navarro County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0087
Grid region
ERCOT (Texas)
Developer
Pisgah Ridge 3, LLC
Connection point (POI)
Tap 345kV 68091 Navarro - 46020 Limestone
Location
Navarro County, Texas
Technology
Battery: 101 MW · Battery
Total requested
101 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
14 July 2021
Proposed online date
December 2026

Location

Marker shows the centre of Navarro County; the queue data does not give exact sites.