United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTRingtail Ridge Storage
Ringtail Ridge Storage is a 101 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Kendall County, Texas.
Queue statusIn planning
- PlanningQueued Jan 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 23INR0163
- Grid region
- ERCOT (Texas)
- Developer
- KCE TX 26, LLC
- Connection point (POI)
- 7150 Kendall 138kV
- Location
- Kendall County, Texas
- Technology
- Battery: 101 MW
- Total requested
- 101 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 25 January 2021
- Proposed online date
- May 2028
Location
Marker shows the centre of Kendall County; the queue data does not give exact sites.
Other requests in Kendall County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem