🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Rock Creek BESS

Rock Creek BESS is a 251 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Kendall County, Texas.

Queue statusConsented
  1. PlanningQueued Feb 2024 (completed)
  2. ConsentedJul 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
26INR0407
Grid region
ERCOT (Texas)
Developer
Flat Rock Energy Center, LLC
Connection point (POI)
7150 Kendall 138kV
Location
Kendall County, Texas
Technology
Battery: 251 MW
Total requested
251 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
27 February 2024
Agreement signed
22 July 2025
Proposed online date
March 2028

Location

Marker shows the centre of Kendall County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Kendall County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem