Big River BESS

Big River BESS is a 51.3 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Zapata County, Texas.

Queue statusIn planning
  1. PlanningQueued May 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0237
Grid region
ERCOT (Texas)
Developer
Rio Grande River Solar LLC
Connection point (POI)
tap 138kV 8299 Zapata - 8957 Lopeno4A
Location
Zapata County, Texas
Technology
Battery: 51.3 MW · Battery
Total requested
51.3 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
4 May 2021
Proposed online date
December 2028

Location

Marker shows the centre of Zapata County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Zapata County