United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESBattery storage interconnection queue in the USA — page 37
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project S0010, Iron County Battery storage · Enterprise Storage LLC |
80.0 MW | Agreement signed |
| Battery storage project S0038, Converse County Battery storage |
80.0 MW | In study |
| Battery storage project S0016, Sevier County Battery storage · Sigurd Storage Acquisitions, L.L.C. |
80.0 MW | Agreement signed |
| Big Star Storage Battery storage · RWE Solar Development, LLC |
80.0 MW | Agreement signed |
| Battery storage project S0011, Iron County Battery storage · Granite Mountain BESS East LLC |
80.0 MW | Agreement signed |
| Battery storage project S0013, Iron County Battery storage · Iron Springs BESS LLC |
80.0 MW | Agreement signed |
| Battery storage project S0009, Beaver County Battery storage · Escalante BESS III LLC |
80.0 MW | Agreement signed |
| Battery storage project J3924, Branch County Battery storage |
80.0 MW | In study |
| Battery storage project GEN-2024-SR10, Lancaster County Battery storage |
80.0 MW | In study |
| Battery storage project AH1-145, Giles County Battery storage · Aries Solar Project LLC |
80.0 MW | In study |
| Battery storage project J2552, Rock Island County Battery storage |
80.0 MW | In study |
| Battery storage project S0031, Box Elder County Battery storage |
80.0 MW | In study |
| Fall Creek Energy Storage Battery storage |
80.0 MW | Agreement signed |
| Battery storage project S0034, Juab County Battery storage |
80.0 MW | In study |
| NYC Energy Battery storage · NYC Energy LLC |
79.9 MW | In study |
| Holtsville Brookhaven Battery Storage Battery storage · Holtsville Brookhaven Battery Storage LLC |
79.9 MW | In study |
| Harlem River Yard Battery storage · Harlem River ESS, LLC |
79.9 MW | In study |
| Bassett Energy Storage Battery storage · Bassett Energy Storage |
79.9 MW | In study |
| Valetudo Energy Storage Battery storage |
79.6 MW | In study |
| Battery storage project GI-SISS-2025-04, Kit Carson County Battery storage |
79.0 MW | In study |
| Luyster Creek Energy Storage 2 Battery storage · Eastern Generation, LLC |
79.0 MW | In study |
| Battery storage project 39508, Laramie County Battery storage |
79.0 MW | In study |
| Kce NY 29 Battery storage · KCE NY 29, LLC |
79.0 MW | In study |
| Hinkell BESS Battery storage · Reveille BESS |
78.1 MW | In study |
| Battery storage project AH1-482, Pulaski County Battery storage · Lightsource Renewable Energy Development, LLC |
78.0 MW | In study |
| Sherbino II BESS SLF Battery storage · Phoenix Battery Storage, LLC |
77.4 MW | Agreement signed |
| Knox County Moore Storage Battery storage · DM-KCM, LLC |
77.0 MW | In study |
| Palmetto Energy Storage Battery storage |
75.6 MW | In study |
| PaleAle BESS Battery storage · Momentum Energy Storage Partners,LLC |
75.4 MW | In study |
| Battery storage project G0717, Klickitat County Battery storage |
75.0 MW | In study |
| Battery storage project GEN-2024-310, Chaves County Battery storage |
75.0 MW | In study |
| Battery storage project AI2-040, Orange County Battery storage |
75.0 MW | In study |
| Battery storage project J1411, Dane County Battery storage |
75.0 MW | Agreement signed |
| Battery storage project Q611, Maricopa County Battery storage |
75.0 MW | In study |
| Battery storage project AI2-041, Halifax County Battery storage |
75.0 MW | In study |
| Battery storage project GEN-2021-052, Muskogee County Battery storage |
75.0 MW | Agreement signed |
| Battery storage project S0018, Tooele County Battery storage |
75.0 MW | In study |
| Battery storage project 1RSC-2020-02, Pueblo County Battery storage |
75.0 MW | Agreement signed |
| Daphne Energy Storage Battery storage · Hanwha Q CELLS USA Corp. |
75.0 MW | In study |
| Battery storage project AH2-227, Jay County Battery storage |
75.0 MW | In study |
| Hummingbird Energy Storage Battery storage |
75.0 MW | Agreement signed |
| Battery storage project GI-2023-178, Imperial County Battery storage |
75.0 MW | In study |
| Battery storage project AI1-130, Baltimore County Battery storage |
75.0 MW | In study |
| Brunswick Battery Storage Battery storage · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
75.0 MW | In study |
| Cerulean Solar and Mulberry BESS Battery storage · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
75.0 MW | Agreement signed |
| Noria Storage Battery storage |
75.0 MW | Paused / redesign |
| Battery storage project Q62, Los Angeles County Battery storage |
75.0 MW | In study |
| Battery storage project 234, Hampton County Battery storage |
75.0 MW | In study |
| Battery storage project Q268, Maricopa County Battery storage |
75.0 MW | Under construction |
| Battery storage project J2550, Yellow Medicine County Battery storage |
75.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)724 · 133.4 GW
- West (non-ISO utilities)352 · 82.2 GW
- MISO (Midcontinent)305 · 55.0 GW
- CAISO (California)175 · 48.7 GW
- SPP (Southwest Power Pool)198 · 31.4 GW
- PJM (Mid-Atlantic, Midwest)248 · 29.6 GW
- Southeast (non-ISO utilities)109 · 19.4 GW
- NYISO (New York)84 · 11.1 GW
- ISO-NE (New England)31 · 6,907 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)