Battery storage project Q62, Los Angeles County

Battery storage project Q62, Los Angeles County is a 75.0 MW battery storage request in interconnection study in the West interconnection queue, in Los Angeles County, California, connecting to Los Angeles Department of Water and Power.

Queue statusIn planning
  1. PlanningQueued Oct 2017 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2020 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q62
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
138kV Bus Station C Wilmington
Location
Los Angeles County, California
Technology
Battery: 75.0 MW
Total requested
75.0 MW
Study phase
FS completed. HS completed. SIS restudy pending.
Queue status
Active
Entered queue
3 October 2017
Proposed online date
June 2020

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.