United States › Grid › Interconnection queues › New York

BATTERY STORAGE · NYISO

Luyster Creek Energy Storage 2

Luyster Creek Energy Storage 2 is a 79.0 MW battery storage request in interconnection study in the NYISO interconnection queue, in Queens County, New York, connecting to ConEd.

Queue statusIn planning
  1. PlanningQueued May 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
834
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
Eastern Generation, LLC
Connection point (POI)
Astoria West 138kV
Location
Queens County, New York
Technology
Battery: 79.0 MW
Total requested
79.0 MW
Study phase
SRIS, FS
Queue status
Active
Entered queue
7 May 2019
Proposed online date
January 2027

Location

Marker shows the centre of Queens County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Queens County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem