🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

BATTERY STORAGE · NYISO

Astoria Energy Storage

Astoria Energy Storage is a 100 MW battery storage request in interconnection study in the NYISO interconnection queue, in Queens County, New York, connecting to ConEd.

Queue statusIn planning
  1. PlanningQueued Oct 2019 (current stage)
  2. ConsentedJan 2023 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
931
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
East River ESS, LLC
Connection point (POI)
Astoria West 138kV
Location
Queens County, New York
Technology
Battery: 100 MW
Total requested
100 MW
Study phase
SRIS, FS
Queue status
Active
Entered queue
28 October 2019
Agreement signed
11 January 2023
Proposed online date
October 2026

Location

Marker shows the centre of Queens County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Queens County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem