BATTERY STORAGE Β· ERCOT

Noria Storage

Noria Storage is a 75.0 MW battery storage request suspended in the ERCOT interconnection queue, in Nueces County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued Aug 2020 (current stage)
  2. ConsentedOct 2022 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0062
Grid region
ERCOT (Texas)
Location
Nueces County, Texas
Technology
Battery: 75.0 MW
Total requested
75.0 MW
Queue status
Suspended
Entered queue
3 August 2020
Agreement signed
12 October 2022
Proposed online date
September 2025

Location

Marker shows the centre of Nueces County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Nueces County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem