United States › Grid › Interconnection queues › Utah
BATTERY STORAGE · WESTBattery storage project S0013, Iron County
Battery storage project S0013, Iron County is a 80.0 MW battery storage request with a signed interconnection agreement in the West interconnection queue, in Iron County, Utah, connecting to PacifiCorp.
Queue statusConsented
- PlanningQueued Mar 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Oct 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- S0013
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Developer
- Iron Springs BESS LLC
- Connection point (POI)
- Three Peaks substation
- Location
- Iron County, Utah
- Technology
- Battery: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed SLGIA 3/25/2024
- Queue status
- Active
- Entered queue
- 23 March 2022
- Proposed online date
- October 2025
Location
Marker shows the centre of Iron County; the queue data does not give exact sites.
Other requests in Iron County
- Solar project 636, Iron CountySolar · 99.0 MW · agreement signed
- Battery storage project S0010, Iron CountyBattery storage · 80.0 MW · agreement signed
- Battery storage project S0011, Iron CountyBattery storage · 80.0 MW · agreement signed
- Battery storage project S0012, Iron CountyBattery storage · 50.0 MW · agreement signed
- Solar + storage project C2-39, Iron CountySolar + storage · 300 MW · in study
- Solar + storage project T2-028, Iron CountySolar + storage · 300 MW · in study
- Solar + storage project PIS049, Iron CountySolar + storage · 300 MW · in study
- Solar + storage project T2-053, Iron CountySolar + storage · 248 MW · in study
- Battery storage project S0017, Iron CountyBattery storage · 200 MW · in study
- Solar + storage project 642, Iron CountySolar + storage · 58.0 MW · in study
- Solar project 763, Iron CountySolar · 200 MW · built
- Solar project 564, Iron CountySolar · 80.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem