Solar project 763, Iron County

Solar project 763, Iron County is a 200 MW solar request built and operating in the West interconnection queue, in Iron County, Utah, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Jun 2016 (completed)
  2. ConsentedJan 2019 (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
763
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Appaloosa Solar I, LLC
Connection point (POI)
Three Peaks substation
Location
Iron County, Utah
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
IA executed 1/7/19
Queue status
Operational
Entered queue
22 June 2016
Agreement signed
7 January 2019
Proposed online date
December 2023

Location

Marker shows the centre of Iron County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Iron County