United States › Grid › Interconnection queues › Utah

SOLAR + STORAGE · WEST

Solar + storage project C2-39, Iron County

Solar + storage project C2-39, Iron County is a 300 MW solar + storage request in interconnection study in the West interconnection queue, in Iron County, Utah, connecting to PacifiCorp.

Queue statusIn planning
  1. PlanningQueued Apr 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
C2-39
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Three Peaks substation
Location
Iron County, Utah
Technology
Solar: 300 MW · Battery
Total requested
300 MW
Service type
Energy only (ERIS)
Queue status
Active
Entered queue
28 April 2022
Proposed online date
December 2025

Location

Marker shows the centre of Iron County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Iron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem