United States › Grid › Interconnection queues › Utah

SOLAR + STORAGE · WEST

Solar + storage project 642, Iron County

Solar + storage project 642, Iron County is a 58.0 MW solar + storage request in interconnection study in the West interconnection queue, in Iron County, Utah, connecting to PacifiCorp.

Queue statusIn planning
  1. PlanningQueued Feb 2015 (current stage)
  2. ConsentedSep 2016 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
642
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Parowan Solar, LLC
Connection point (POI)
Parowan substation
Location
Iron County, Utah
Technology
Solar: 58.0 MW · Battery
Total requested
58.0 MW
Service type
Energy only (ERIS)
Study phase
IA signed 9/8/16, suspended 12/11/2024
Queue status
Active
Entered queue
9 February 2015
Agreement signed
8 September 2016
Proposed online date
December 2024

Location

Marker shows the centre of Iron County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Iron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem