🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

BATTERY STORAGE · PJM

Battery storage project AH1-145, Giles County

Battery storage project AH1-145, Giles County is a 80.0 MW battery storage request in interconnection study in the PJM interconnection queue, in Giles County, Virginia, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH1-145
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
Aries Solar Project LLC
Connection point (POI)
Peter's Mountain 138 kV
Location
Giles County, Virginia
Technology
Battery: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
7 March 2025
Proposed online date
December 2024

Location

Marker shows the centre of Giles County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Giles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem