OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) — page 32

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3,261621.9 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3,261 requests · page 32 of 66
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2432, Tunica County
Solar
150 MWWithdrawn / abandoned Tunica, MSMISO Sep 2022target 2026
Onshore wind project J3332, Calumet County
Onshore wind
150 MWWithdrawn / abandoned Calumet, WIMISO Apr 2024target 2028
Solar project J1689, Henry County
Solar
150 MWWithdrawn / abandoned Henry, INMISO Jun 2020target 2023
Onshore wind project G413, Mclean County
Onshore wind
150 MWWithdrawn / abandoned Mclean, ILMISO Mar 2004target 2006
Solar project J2792, Concordia Parish County
Solar
150 MWWithdrawn / abandoned Concordia Parish, LAMISO Aug 2022target 2026
Onshore wind project G154, Deuel County
Onshore wind
150 MWWithdrawn / abandoned Deuel, SDMISO Nov 2001target 2003
Battery storage project J1446, Wright County
Battery storage
150 MWWithdrawn / abandoned Wright, MNMISO Apr 2019target 2022
Solar + storage project J2279, Ionia County
Solar + storage
150 MWWithdrawn / abandoned Ionia, MIMISO Jul 2021target 2025
Solar project J1414, Clay County
Solar
150 MWWithdrawn / abandoned Clay, ARMISO Apr 2019target 2022
Onshore wind project H019, Watonwan County
Onshore wind
150 MWWithdrawn / abandoned Watonwan, MNMISO Apr 2008target 2010
Onshore wind project J738, Green County
Onshore wind
150 MWWithdrawn / abandoned Green, WIMISO Nov 2016target 2020
Onshore wind project J2040, Dickinson County
Onshore wind
150 MWWithdrawn / abandoned Dickinson, IAMISO Aug 2021target 2024
Solar project J2671, Arenac County
Solar
150 MWWithdrawn / abandoned Arenac, MIMISO Sep 2022target 2025
Onshore wind project J1400, Crittenden County
Onshore wind
150 MWWithdrawn / abandoned Crittenden, ARMISO Apr 2019target 2021
Solar project J1088, Shiawassee County
Solar
150 MWWithdrawn / abandoned Shiawassee, MIMISO Mar 2018target 2021
Solar project J698, Chicot County
Solar
150 MWWithdrawn / abandoned Chicot, ARMISO Jun 2017target 2015
Onshore wind project J085, Hillsdale County
Onshore wind
150 MWWithdrawn / abandoned Hillsdale, MIMISO Oct 2009target 2012
Solar project J4008, Henry County
Solar
150 MWWithdrawn / abandoned Henry, INMISO May 2025target 2027
Battery storage project J3618, Clay County
Battery storage
150 MWWithdrawn / abandoned Clay, ARMISO Apr 2024target 2028
Solar project J990, Dubuque County
Solar
150 MWWithdrawn / abandoned Dubuque, IAMISO Mar 2018target 2020
Battery storage project J3432, Lawrence County
Battery storage
150 MWWithdrawn / abandoned Lawrence, ILMISO Apr 2024target 2028
Onshore wind project J931, Ottawa County
Onshore wind
150 MWWithdrawn / abandoned Ottawa, MIMISO Jun 2017target 2021
Onshore wind project J452, Sanilac County
Onshore wind
150 MWWithdrawn / abandoned Sanilac, MIMISO May 2015
Solar project J3652, Lenawee County
Solar
150 MWWithdrawn / abandoned Lenawee, MIMISO Apr 2024target 2028
Onshore wind project G740, Howard County
Onshore wind
150 MWWithdrawn / abandoned Howard, IAMISO Feb 2007target 2012
Battery storage project J3622, Craighead County
Battery storage
150 MWWithdrawn / abandoned Craighead, ARMISO Apr 2024target 2028
Solar + storage project J3413, Pulaski County
Solar + storage
150 MWWithdrawn / abandoned Pulaski, ARMISO Mar 2024target 2028
Replacing 150 MW of storage with solar/storage hybrid; Williams Solar
Other
150 MWWithdrawn / abandoned Jefferson, INMISO May 2024target 2025
Solar project J1811, Independence County
Solar
150 MWWithdrawn / abandoned Independence, ARMISO Jun 2020target 2023
Onshore wind project J098, Dickey County
Onshore wind
150 MWWithdrawn / abandoned Dickey, NDMISO Nov 2009target 2012
Solar project J1156, Crittenden County
Solar
150 MWWithdrawn / abandoned Crittenden, ARMISO Mar 2018target 2020
Solar project J3927, Sheboygan County
Solar
150 MWWithdrawn / abandoned Sheboygan, WIMISO Feb 2025target 2028
Onshore wind project G854, Mason County
Onshore wind
150 MWWithdrawn / abandoned Mason, MIMISO Sep 2007target 2010
Solar project J2610, Bond County
Solar
150 MWWithdrawn / abandoned Bond, ILMISO Sep 2022target 2026
Onshore wind project R66, Adams County
Onshore wind
150 MWWithdrawn / abandoned Adams, IAMISO Apr 2009target 2010
Solar project J1462, Acadia Parish County
Solar
150 MWWithdrawn / abandoned Acadia Parish, LAMISO Apr 2019target 2022
Solar + storage project J3317, Vigo County
Solar + storage
150 MWWithdrawn / abandoned Vigo, INMISO Apr 2024target 2028
Onshore wind project J2019, Rolette County
Onshore wind
150 MWWithdrawn / abandoned Rolette, NDMISO Aug 2021target 2025
Solar project J3673, Newton County
Solar
150 MWWithdrawn / abandoned Newton, INMISO Apr 2024target 2028
Onshore wind project J3328, Vermilion County
Onshore wind
150 MWWithdrawn / abandoned Vermilion, ILMISO Apr 2024target 2028
Onshore wind project J1371, Yellow Medicine County
Onshore wind
150 MWWithdrawn / abandoned Yellow Medicine, MNMISO Apr 2019target 2023
Onshore wind project J2256, Humboldt County
Onshore wind
150 MWWithdrawn / abandoned Humboldt, IAMISO Aug 2021target 2024
Solar project J1625, Tipton County
Solar
150 MWWithdrawn / abandoned Tipton, INMISO Aug 2021target 2024
Onshore wind project J563, Marshall County
Onshore wind
150 MWWithdrawn / abandoned Marshall, IAMISO May 2016
Onshore wind project G908, Morgan County
Onshore wind
150 MWWithdrawn / abandoned Morgan, ILMISO Mar 2009target 2009
Onshore wind project J3363, Tensas Parish County
Onshore wind
150 MWWithdrawn / abandoned Tensas Parish, LAMISO Apr 2024target 2028
Solar project J3476, St. Croix County
Solar
150 MWWithdrawn / abandoned St. Croix, WIMISO Apr 2024target 2028
Solar + storage project J3582, Beauregard Parish County
Solar + storage
150 MWWithdrawn / abandoned Beauregard Parish, LAMISO Apr 2024target 2028
Onshore wind project J1118, Piatt County
Onshore wind
150 MWWithdrawn / abandoned Piatt, ILMISO Mar 2018target 2021
Onshore wind project J570, Atchison County
Onshore wind
150 MWWithdrawn / abandoned Atchison, MOMISO May 2016target 2018
Page 32 of 66

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)