Solar + storage project J3413, Pulaski County

Solar + storage project J3413, Pulaski County is a 150 MW solar + storage request withdrawn in the MISO interconnection queue, in Pulaski County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2024 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3413
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
L.R. 145TH ST - L.R. PORT 115.0kV
Location
Pulaski County, Arkansas
Technology
Solar: 150 MW Β· Battery
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
29 March 2024
Proposed online date
July 2028
Withdrawn
December 2025

Location

Marker shows the centre of Pulaski County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Pulaski County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem