πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

SOLAR Β· MISO

Solar project J3652, Lenawee County

Solar project J3652, Lenawee County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Lenawee County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3652
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
BEECHER - KNOWLES 138.0kV
Location
Lenawee County, Michigan
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
16 April 2024
Proposed online date
September 2028
Withdrawn
December 2025

Location

Marker shows the centre of Lenawee County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Lenawee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem