United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA (2024 requests) — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,283285.2 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,283 requests · page 3 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project IC-1247, Heard County
Battery storage
500 MWAgreement signed Heard, GASoutheast Mar 2024target 2028
Onshore wind project 5RSC-2024-15, Kiowa County
Onshore wind
500 MWIn study Kiowa, COWest Jan 2024target 2027
Battery storage project Company QQ, Washoe County
Battery storage
500 MWIn study Washoe, NVWest Mar 2024target 2028
Solar + storage project NC5-010, Kane County
Solar + storage
500 MWIn study Kane, UTWest Mar 2024target 2028
Battery storage project 2024-MP1, Mohave County
Battery storage
500 MWIn study Mohave, AZWest Jan 2024target 2028
Solar project J3532, Roseau County
Solar
500 MWIn study Roseau, MNMISO Apr 2024target 2028
Solar + storage project Q111, Clark County
Solar + storage
500 MWIn study Clark, NVWest Jun 2024target 2026
Onshore wind project 5RSC-2024-28, Kit Carson County
Onshore wind
500 MWIn study Kit Carson, COWest Jan 2024target 2025
Gas project GEN-2024-013, Mcclain County
Gas
496 MWIn study Mcclain, OKSPP Aug 2024target 2030
Gas project GEN-2024-GR1, Oklahoma County
Gas
492 MWAgreement signed Oklahoma, OKSPP Jan 2024target 2026
North Royal Thermal (TEF- Due Diligence)
Gas · Invenergy Energy Transition Development LLC
479 MWIn study Lamar, TXERCOT Jun 2024target 2030
Mirando Valley Wind
Onshore wind · ACE DevCo NC LLC
479 MWIn study Jim Hogg, TXERCOT Aug 2024target 2028
Gas project J3331, Sullivan County
Gas
470 MWIn study Sullivan, INMISO Apr 2024target 2028
Gregory Power Development SLF
Gas · Gregory Power Partners LLC
470 MWIn study San Patricio, TXERCOT Nov 2024target 2028
Gas project GI-121, Randolph County
Gas
460 MWAgreement signed Randolph, MOSoutheast May 2024target 2030
Gas project 960889, Rowan County
Gas
455 MWIn study Rowan, NCSoutheast Jun 2024
Gas project 961188, Stokes County
Gas
455 MWIn study Stokes, NCSoutheast Jun 2024
Gas project 961210, Stokes County
Gas
455 MWIn study Stokes, NCSoutheast Jun 2024
Gas project 956747, Rowan County
Gas
455 MWIn study Rowan, SCSoutheast Jun 2024
Cedar Draw Solar
Solar + storage · Cedar Draw Solar LLC
451 MWIn study Scurry, TXERCOT Mar 2024target 2027
Onshore wind project 5RSC-2024-16, Cheyenne County
Onshore wind
450 MWIn study Cheyenne, COWest Jan 2024target 2026
Other project Q567, Maricopa County
Other
450 MWIn study Maricopa, AZWest May 2024target 2028
Zeus Spade BESS
Wind + storage · Spade BESS
446 MWIn study Mitchell, TXERCOT Mar 2024target 2027
Onshore wind project J3730, Macoupin County
Onshore wind
444 MWIn study Macoupin, ILMISO Apr 2024target 2028
Vast Sands Power II (TEF-Due Diligence)
Gas · Permian Power I LLC
440 MWAgreement signed Ward, TXERCOT Jul 2024target 2028
Vast Sands Power I (TEF -Due Diligence)
Gas · Permian Power I LLC
440 MWAgreement signed Ward, TXERCOT Jul 2024target 2028
Solar project J3762, Clay County
Solar
430 MWIn study Clay, MNMISO Apr 2024target 2028
Other project Q560, Maricopa County
Other
425 MWIn study Maricopa, AZWest May 2024target 2028
Onshore wind project GI-2024-13, Adams County
Onshore wind
423 MWIn study Adams, COWest May 2024target 2028
Onshore wind project GI-2024-12, Adams County
Onshore wind
423 MWIn study Adams, COWest May 2024target 2028
Windecker
Onshore wind · Windecker Energy LLC
420 MWIn study Upton, TXERCOT Mar 2024target 2028
Gamay Energy Storage
Battery storage · GAMAY ENERGY STORAGE LLC
419 MWAgreement signed Brazoria, TXERCOT Feb 2024target 2027
Bypass BESS II
Battery storage · Bypass BESS II LLC
416 MWIn study Fort Bend, TXERCOT Nov 2024target 2027
Western Flats Storage
Solar + storage · Hecate Energy Point Mountain Solar Facility 1 LLC
411 MWIn study Crane, TXERCOT Apr 2024target 2028
Operation Sunshine Storage
Solar + storage · Duck Creek Storage, LLC
410 MWAgreement signed Concho, TXERCOT Feb 2024target 2028
Battery storage project Q2413, Pinal County
Battery storage
409 MWIn study Pinal, AZWest Feb 2024target 2027
Ulysses Crossing Solar
Solar
405 MWPaused / redesign Coleman, TXERCOT Sep 2024
Big Rooter West Solar
Solar + storage · Big Rooter West, LLC
403 MWAgreement signed Robertson, TXERCOT Mar 2024target 2028
Hittson Creek Solar
Solar + storage · 174 Power Global Properties
403 MWIn study Callahan, TXERCOT Dec 2024target 2028
Solarville Solar SLF
Solar + storage · Ville Solar, LLC
403 MWIn study Kaufman, TXERCOT May 2024target 2028
Bernice Energy Storage
Battery storage · Bernice Energy Storage LLC
403 MWIn study Bexar, TXERCOT Sep 2024target 2027
Bluefox Solar 1
Solar · Industrial November Project LLC
403 MWIn study Matagorda, TXERCOT Mar 2024target 2029
Bluefox Solar 2
Solar · Industrial November Project LLC
402 MWIn study Matagorda, TXERCOT Mar 2024target 2030
Infinium Solar
Solar · Jackalope Flats Solar, LLC
402 MWIn study Howard, TXERCOT Aug 2024target 2029
Corruscant BESS
Battery storage · AEU Battery Project III LLC
402 MWIn study Dickens, TXERCOT Feb 2024target 2027
Battery storage project 620, Bay County
Battery storage · FPL
400 MWIn study Bay, FLSoutheast Jan 2024target 2026
Solar + storage project GI-2024-05, Pueblo County
Solar + storage
400 MWIn study Pueblo, COWest Apr 2024target 2028
Gas project 5RSC-2024-02, Weld County
Gas
400 MWIn study Weld, COWest Jan 2024target 2027
Onshore wind project J3712, Peoria County
Onshore wind
400 MWIn study Peoria, ILMISO Apr 2024target 2028
Onshore wind project J3701, Taylor County
Onshore wind
400 MWIn study Taylor, IAMISO Apr 2024target 2028
Page 3 of 26

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)