United States › Grid › Interconnection queues › Colorado

ONSHORE WIND · WEST

Onshore wind project GI-2024-13, Adams County

Onshore wind project GI-2024-13, Adams County is a 423 MW onshore wind request in interconnection study in the West interconnection queue, in Adams County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusIn planning
  1. PlanningQueued May 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-2024-13
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Pawnee 345 kV Substation
Location
Adams County, Colorado
Technology
Wind: 423 MW
Total requested
423 MW
Service type
Energy only (ERIS)
Study phase
Detailed status: Study to be started after completion of 5RSC
Queue status
Active
Entered queue
14 May 2024
Proposed online date
December 2028

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem