🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Nevada

SOLAR + STORAGE · WEST

Solar + storage project Q111, Clark County

Solar + storage project Q111, Clark County is a 500 MW solar + storage request in interconnection study in the West interconnection queue, in Clark County, Nevada, connecting to Los Angeles Department of Water and Power.

Queue statusIn planning
  1. PlanningQueued Jun 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q111
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
Marketplace 500kV Switching Station
Location
Clark County, Nevada
Technology
Solar: 250 MW · Battery: 250 MW
Total requested
500 MW
Study phase
Application received
Queue status
Active
Entered queue
27 June 2024
Proposed online date
June 2026

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem