Withdrawn queue requests in the USA (2019 requests) โ€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,473226.5 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,473 requests ยท page 3 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GI-2019-1, El Paso County
Solar
450 MWWithdrawn / abandoned El Paso, COWest Feb 2019target 2021
Solar + storage project Company KF, Pershing County
Solar + storage
450 MWWithdrawn / abandoned Pershing, NVWest Oct 2019target 2022
Solar project G0610, Sherman County
Solar
450 MWWithdrawn / abandoned Sherman, ORWest Jan 2019target 2021
Triumph Solar
Solar + storage
450 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2023
Solar project GI-85, Dade County
Solar
436 MWWithdrawn / abandoned Dade, MOSoutheast Sep 2019target 2027
Trestles Energy Storage
Battery storage
434 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2019target 2022
Solar + storage project Company 180, Clark County
Solar + storage
425 MWWithdrawn / abandoned Clark, NVWest Sep 2019target 2022
Boulder Oaks Hybrid
Wind + storage
411 MWWithdrawn / abandoned San Diego, CACAISO Apr 2019target 2023
Larisa Solar
Solar ยท ABEI ENERGY & INFRASTRUCTURE LLC
408 MWWithdrawn / abandoned Jones, TXERCOT Apr 2019target 2024
Doradus
Solar + storage
406 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Rigal
Solar + storage
406 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Ash Tree Hybrid Solar
Solar + storage
406 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2022
Familia Hybrid Solar
Solar + storage
405 MWWithdrawn / abandoned Maricopa, CACAISO Apr 2019target 2022
Onshore wind project GEN-2019-029, Keith County
Onshore wind
404 MWWithdrawn / abandoned Keith, NESPP Apr 20192024
Garces Hybrid Solar
Solar + storage
403 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Agua Amarga Wind
Onshore wind
403 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2023
DRY Grape Hybrid Solar
Solar + storage
403 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2022
Battery storage project 1166, Box Elder County
Battery storage
400 MWWithdrawn / abandoned Box Elder, UTWest Sep 2019target 2021
Yellow Hay Hybrid Solar
Solar + storage
400 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2022
Solar project AE2-311, Sussex County
Solar
400 MWWithdrawn / abandoned Sussex, VAPJM Mar 2019target 2021
Onshore wind project J1427, Benton County
Onshore wind
400 MWWithdrawn / abandoned Benton, IAMISO Apr 2019target 2022
Solar + storage project Q72, San Bernardino County
Solar + storage
400 MWWithdrawn / abandoned San Bernardino, CAWest Jul 2019target 2021
Onshore wind project AE2-232, Atlantic County
Onshore wind
400 MWWithdrawn / abandoned Atlantic, NJPJM Mar 2019target 2023
Solar + storage project Q12, Pinal County
Solar + storage
400 MWWithdrawn / abandoned Pinal, AZWest Jan 2019target 2023
Battery storage project GEN-2019-064, Swisher County
Battery storage
400 MWWithdrawn / abandoned Swisher, TXSPP May 2019target 2024
Solar project 2, Sacramento County
Solar
400 MWWithdrawn / abandoned Sacramento, CAWest Oct 2019target 2023
Solar project GEN-2019-028, Lincoln County
Solar
400 MWWithdrawn / abandoned Lincoln, NESPP Apr 20192025
Onshore wind project 1183, Carbon County
Onshore wind
400 MWWithdrawn / abandoned Carbon, WYWest Oct 2019target 2024
Solar + storage project AE2-149, Pickaway County
Solar + storage
400 MWWithdrawn / abandoned Pickaway, OHPJM Mar 2019target 2022
Onshore wind project J1341, Buchanan County
Onshore wind
398 MWWithdrawn / abandoned Buchanan, IAMISO Apr 2019target 2022
Ion Solar
Solar ยท GSE Group LLC
384 MWWithdrawn / abandoned ERCOT May 2019target 2026
Gas project J1346, Wayne County
Gas
382 MWWithdrawn / abandoned Wayne, MIMISO Apr 2019target 2022
Onshore wind project 1156, Carbon County
Onshore wind
380 MWWithdrawn / abandoned Carbon, WYWest Aug 2019target 2023
Simple Cycle Combustion Turbine Repowering (alternative to Q647)
Gas
378 MWWithdrawn / abandoned Middlesex, CTISO-NE Apr 2019target 2023
Draco Solar
Solar + storage
375 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2023
Queue Power Plant
Gas ยท Pro Energy Services LLC
363 MWWithdrawn / abandoned Galveston, TXERCOT Jan 2019target 2021
Toland Power Plant
Gas ยท ProEnergy Services LLC
363 MWWithdrawn / abandoned San Patricio, TXERCOT Feb 2019target 2020
Peony
Solar
359 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Journey Storage
Battery storage
355 MWWithdrawn / abandoned Kings, CACAISO Apr 2019target 2022
Columbia Solar Energy Center
Solar ยท EDF Renewables Development, Inc.
350 MWWithdrawn / abandoned Herkimer, NYNYISO May 2019
Solar project Company 177, Clark County
Solar
350 MWWithdrawn / abandoned Clark, NVWest Mar 2019target 2023
Solar + storage project 1118, Moffat County
Solar + storage
350 MWWithdrawn / abandoned Moffat, COWest Mar 2019target 2023
Solar + storage project AF1-070, Clark County
Solar + storage
350 MWWithdrawn / abandoned Clark, KYPJM Aug 2019target 2022
Solar project GI-2019-2, Pueblo County
Solar
350 MWWithdrawn / abandoned Pueblo, COWest Feb 2019target 2021
Ridge View Solar Energy Center
Solar ยท EDF Renewables Development, Inc.
350 MWWithdrawn / abandoned Niagara, NYNYISO May 2019
Paddlefish Solar
Solar + storage
350 MWWithdrawn / abandoned Wells, INPJM Sep 2019target 2029
Solar project IC-794, Turner County
Solar
343 MWWithdrawn / abandoned Turner, GASoutheast May 2019
Other project J1349, Cottonwood County
Other
335 MWWithdrawn / abandoned Cottonwood, MNMISO Apr 2019target 2023
Dexter Solar
Solar ยท 241BB 8me LLC
330 MWWithdrawn / abandoned Runnels, TXERCOT Mar 2019target 2023
Dexter Storage
Other ยท 241BB 8ME LLC
325 MWWithdrawn / abandoned Runnels, TXERCOT Aug 2019target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)