United States βΊ Grid βΊ Interconnection queues βΊ Nebraska
SOLAR Β· SPPSolar project GEN-2019-028, Lincoln County
Solar project GEN-2019-028, Lincoln County is a 400 MW solar request withdrawn in the SPP interconnection queue, in Lincoln County, Nebraska, connecting to NPPD.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedDec 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2025 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2019-028
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NPPD
- Connection point (POI)
- Gerald Gentlemen 345kV Substation
- Location
- Lincoln County, Nebraska
- Technology
- Solar: 400 MW
- Total requested
- 400 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 23 April 2019
- Proposed online date
- December 2025
- Came online
- December 2025
- Withdrawn
- December 2022
Location
Marker shows the centre of Lincoln County; the queue data does not give exact sites.
Other requests in Lincoln County
- Solar project GEN-2020-051, Lincoln CountySolar Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2007-010N05, Lincoln CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project GEN-2007-010N, Lincoln CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project GEN-2007-010N03, Lincoln CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project GEN-2007-010N04, Lincoln CountyOnshore wind Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem