Solar project IC-794, Turner County

Solar project IC-794, Turner County is a 343 MW solar request withdrawn in the Southeast interconnection queue, in Turner County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2019 (completed)
  2. Withdrawn / abandonedNov 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-794
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
North Tifton - Pitts 230 kV Line
Location
Turner County, Georgia
Technology
Solar: 343 MW
Total requested
343 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
16 May 2019
Withdrawn
November 2019

Location

Marker shows the centre of Turner County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Turner County