Solar project IC-641, Turner County

Solar project IC-641, Turner County is a 111 MW solar request withdrawn in the Southeast interconnection queue, in Turner County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedJun 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-641
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
North Tifton - Pitts 230 kV Line
Location
Turner County, Georgia
Technology
Solar: 111 MW
Total requested
111 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
17 May 2017
Withdrawn
June 2023

Location

Marker shows the centre of Turner County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Turner County