Solar project IC-640, Turner County

Solar project IC-640, Turner County is a 155 MW solar request withdrawn in the Southeast interconnection queue, in Turner County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedSep 2021 (project stopped here)
  3. ConsentedFeb 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-640
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
North Tifton - Pitts 230 kV Line
Location
Turner County, Georgia
Technology
Solar: 155 MW
Total requested
155 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
10 May 2017
Agreement signed
21 February 2019
Withdrawn
September 2021

Location

Marker shows the centre of Turner County; the queue data does not give exact sites.