Solar project GI-85, Dade County

Solar project GI-85, Dade County is a 436 MW solar request withdrawn in the Southeast interconnection queue, in Dade County, Missouri, connecting to Associated Electric Cooperative, Incorporated.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2019 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-85
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Associated Electric Cooperative, Incorporated
Connection point (POI)
Morgan 345 kV
Location
Dade County, Missouri
Technology
Solar: 436 MW
Total requested
436 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
27 September 2019
Proposed online date
September 2027

Location

Marker shows the centre of Dade County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Dade County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem