Onshore wind project GI-95, Dade County

Onshore wind project GI-95, Dade County is a 247 MW onshore wind request with a signed interconnection agreement in the Southeast interconnection queue, in Dade County, Missouri, connecting to Associated Electric Cooperative, Incorporated.

Queue statusConsented
  1. PlanningQueued Dec 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GI-95
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Associated Electric Cooperative, Incorporated
Connection point (POI)
Jasper-Morgan 345 kV
Location
Dade County, Missouri
Technology
Wind: 247 MW
Total requested
247 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Active
Entered queue
4 December 2020
Proposed online date
December 2026

Location

Marker shows the centre of Dade County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri

Other requests in Dade County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem