πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

SOLAR + STORAGE Β· SPP

Solar + storage project GEN-2024-064, Dade County

Solar + storage project GEN-2024-064, Dade County is a 185 MW solar + storage request withdrawn in the SPP interconnection queue, in Dade County, Missouri, connecting to EDE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2024 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2024-064
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
EDE
Connection point (POI)
Dadeville - Chesapeake 161 kV line
Location
Dade County, Missouri
Technology
Solar: 185 MW Β· Battery
Total requested
185 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 October 2024
Proposed online date
August 2030

Location

Marker shows the centre of Dade County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Dade County