United States › Grid › Interconnection queues › Wisconsin
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Wisconsin — page 3
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project J1497, Jefferson County Solar |
125 MW | Withdrawn / abandoned |
| Onshore wind project J1866, Clark County Onshore wind |
125 MW | Withdrawn / abandoned |
| Solar project J798, Walworth County Solar |
124 MW | Withdrawn / abandoned |
| Solar project J3433, Barron County Solar |
115 MW | Withdrawn / abandoned |
| Battery storage project J2621, St. Croix County Battery storage |
115 MW | Withdrawn / abandoned |
| Battery storage project J2365, Portage County Battery storage |
115 MW | Withdrawn / abandoned |
| Other project G161, Iron County Other |
110 MW | Withdrawn / abandoned |
| Gas project G249, Shawano County Gas |
110 MW | Withdrawn / abandoned |
| Onshore wind project J314, Columbia County Onshore wind |
101 MW | Withdrawn / abandoned |
| Onshore wind project G977, Calumet County Onshore wind |
101 MW | Withdrawn / abandoned |
| Onshore wind project J315, Rock County Onshore wind |
101 MW | Withdrawn / abandoned |
| Onshore wind project J657, Manitowoc County Onshore wind |
101 MW | Withdrawn / abandoned |
| Solar project J1160, Adams County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project J2074, Outagamie County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar project J1740, Walworth County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J668, Waushara County Solar |
100 MW | Withdrawn / abandoned |
| Gas project G222, Burnett County Gas |
100 MW | Withdrawn / abandoned |
| Other project G303, Columbia County Other |
100 MW | Withdrawn / abandoned |
| Solar project J1510, Wood County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J1253, Fond Du Lac County Solar |
100 MW | Withdrawn / abandoned |
| Onshore wind project G506, Monroe County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project G546, Walworth County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project G378, Rock County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project G379, Walworth County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project G289, Rock County Onshore wind |
100 MW | Withdrawn / abandoned |
| Battery storage project J3161, Sheboygan County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar project J2062, Columbia County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project J2537, Shawano County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar project J2070, St. Croix County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J2303, Waushara County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J1955, Walworth County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project J2014, Clark County Battery storage |
100 MW | Withdrawn / abandoned |
| Battery storage project J1930, Columbia County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar project J1711, Green County Solar |
100 MW | Withdrawn / abandoned |
| Other project G147, Iowa County Other |
100 MW | Withdrawn / abandoned |
| Onshore wind project G793, Rock County Onshore wind |
100 MW | Withdrawn / abandoned |
| Battery storage project J1104, Washington County Battery storage |
100 MW | Withdrawn / abandoned |
| Onshore wind project G747, Rock County Onshore wind |
100 MW | Withdrawn / abandoned |
| Battery storage project J2557, Wood County Battery storage |
100 MW | Withdrawn / abandoned |
| Other project G115, Juneau County Other |
100 MW | Withdrawn / abandoned |
| Solar project J1716, Fond Du Lac County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J1596, Waushara County Solar |
100 MW | Withdrawn / abandoned |
| Onshore wind project G288, Walworth County Onshore wind |
100 MW | Withdrawn / abandoned |
| Solar project J1719, Waushara County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project J1928, Grant County Battery storage |
100 MW | Withdrawn / abandoned |
| Onshore wind project G371, Columbia County Onshore wind |
100 MW | Withdrawn / abandoned |
| Solar project J669, Portage County Solar |
100 MW | Withdrawn / abandoned |
| Onshore wind project J814, Clark County Onshore wind |
99.9 MW | Withdrawn / abandoned |
| Onshore wind project J819, Lafayette County Onshore wind |
99.9 MW | Withdrawn / abandoned |
| Onshore wind project J821, Marathon County Onshore wind |
99.9 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)