United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

BATTERY STORAGE Β· MISO

Battery storage project J1104, Washington County

Battery storage project J1104, Washington County is a 100 MW battery storage request withdrawn in the MISO interconnection queue, in Washington County, Wisconsin, connecting to American Transmission Co..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedOct 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1104
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Germantown - Bark River 138kV Line
Location
Washington County, Wisconsin
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
September 2021
Withdrawn
October 2019

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem