United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

ONSHORE WIND Β· MISO

Onshore wind project G379, Walworth County

Onshore wind project G379, Walworth County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Walworth County, Wisconsin.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2003 (completed)
  2. Withdrawn / abandonedFeb 2004 (project stopped here)
  3. ConsentedFeb 2004 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G379
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Walworth County, Wisconsin
Technology
Wind: 100 MW
Total requested
100 MW
Queue status
Withdrawn
Entered queue
20 November 2003
Agreement signed
17 February 2004
Proposed online date
November 2005
Withdrawn
February 2004

Location

Marker shows the centre of Walworth County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Walworth County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem