SOLAR · MISOSolar project J2666, Walworth County
Solar project J2666, Walworth County is a 100 MW solar request in interconnection study in the MISO interconnection queue, in Walworth County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
- PlanningQueued Jan 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2666
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Brick Church 138 kV
- Location
- Walworth County, Wisconsin
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 9 January 2024
- Proposed online date
- June 2026
Location
Marker shows the centre of Walworth County; the queue data does not give exact sites.
Other requests in Walworth County
- Gas project J4116, Walworth CountyGas · 950 MW · in study
- Gas project J4028, Walworth CountyGas · 324 MW · in study
- Other project G138, Walworth CountyOther · 352 MW · withdrawn
- Solar project J1044, Walworth CountySolar · 200 MW · withdrawn
- Solar project J1047, Walworth CountySolar · 200 MW · withdrawn
- Solar project J1042, Walworth CountySolar · 200 MW · withdrawn
- Solar project J798, Walworth CountySolar · 124 MW · withdrawn
- Solar project J1740, Walworth CountySolar · 100 MW · withdrawn
- Onshore wind project G546, Walworth CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project G379, Walworth CountyOnshore wind · 100 MW · withdrawn
- Solar project J1955, Walworth CountySolar · 100 MW · withdrawn
- Onshore wind project G288, Walworth CountyOnshore wind · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem