SOLAR Β· MISO

Solar project J1160, Adams County

Solar project J1160, Adams County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Adams County, Wisconsin, connecting to American Transmission Co..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedJan 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1160
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Sand Lake - Port Edwards 138 kV Line Tap
Location
Adams County, Wisconsin
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
October 2021
Withdrawn
January 2019

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.