United States βΊ Grid βΊ Interconnection queues βΊ Wisconsin
SOLAR Β· MISOSolar project J1160, Adams County
Solar project J1160, Adams County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Adams County, Wisconsin, connecting to American Transmission Co..
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandonedJan 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1160
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- American Transmission Co.
- Connection point (POI)
- Sand Lake - Port Edwards 138 kV Line Tap
- Location
- Adams County, Wisconsin
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 12 March 2018
- Proposed online date
- October 2021
- Withdrawn
- January 2019
Location
Marker shows the centre of Adams County; the queue data does not give exact sites.
Power plants in Wisconsin Β· Transmission lines in Wisconsin
Other requests in Adams County