United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

ONSHORE WIND Β· MISO

Onshore wind project G793, Rock County

Onshore wind project G793, Rock County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Rock County, Wisconsin.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2007 (completed)
  2. Withdrawn / abandonedApr 2009 (project stopped here)
  3. ConsentedApr 2009 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G793
Grid region
MISO (Midcontinent)
Connection point (POI)
Rock River - SW Delavan 138 kV
Location
Rock County, Wisconsin
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
30 April 2007
Agreement signed
8 April 2009
Proposed online date
December 2007
Withdrawn
April 2009

Location

Marker shows the centre of Rock County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Rock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem