Solar project J669, Portage County

Solar project J669, Portage County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Portage County, Wisconsin.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2016 (completed)
  2. Withdrawn / abandonedJul 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J669
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Portage County, Wisconsin
Technology
Solar: 100 MW
Total requested
100 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
11 July 2016
Proposed online date
August 2018
Withdrawn
July 2017

Location

Marker shows the centre of Portage County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Portage County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem