BATTERY STORAGE Β· MISO

Battery storage project J2335, Portage County

Battery storage project J2335, Portage County is a 200 MW battery storage request withdrawn in the MISO interconnection queue, in Portage County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2335
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMERICAN TRANSMISSION COMPANY
Connection point (POI)
Plover 115 kV Substation (J1573 substation)
Location
Portage County, Wisconsin
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
14 September 2022
Proposed online date
September 2025
Withdrawn
July 2025

Location

Marker shows the centre of Portage County; the queue data does not give exact sites.