United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2019 requests) โ€” page 26

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,473226.5 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,473 requests ยท page 26 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Bolivar Solar
Solar
19.3 MWWithdrawn / abandoned Stark, OHPJM Mar 2019target 2026
Peconic River II
Battery storage ยท Energy Storage Resources, LLC
19.2 MWWithdrawn / abandoned Suffolk, NYNYISO Jun 2019
Queen City
Battery storage ยท Energy Storage Resources, LLC
19.2 MWWithdrawn / abandoned Dutchess, NYNYISO Jun 2019
Meredith Woods
Battery storage ยท Energy Storage Resources, LLC
19.2 MWWithdrawn / abandoned New York, NYNYISO Jun 2019
Battery storage project AF1-231, Accomack County
Battery storage
19.0 MWWithdrawn / abandoned Accomack, VAPJM Sep 2019target 2022
Reiher Solar II
Solar ยท EnergieKontor US Texas SP 7 LLC
18.4 MWWithdrawn / abandoned Upton, TXERCOT Jun 2019target 2021
Solar
Solar
18.4 MWWithdrawn / abandoned York, MEISO-NE Dec 2019target 2021
Solar project AF1-250, Mercer County
Solar
18.0 MWWithdrawn / abandoned Mercer, PAPJM Sep 2019target 2022
Battery storage project AF1-082, Edgecombe County
Battery storage
18.0 MWWithdrawn / abandoned Edgecombe, NCPJM Aug 2019target 2020
Battery storage project AE2-207, Edgecombe County
Battery storage
18.0 MWWithdrawn / abandoned Edgecombe, NCPJM Mar 2019target 2020
Snyder BESS
Other ยท Snyder Wind Farm, LLC
17.6 MWWithdrawn / abandoned Scurry, TXERCOT Mar 2019target 2021
Hornell Center 16
Solar ยท Sky Solar Inc.
17.6 MWWithdrawn / abandoned Allegany, NYNYISO Jun 2019
Pembroke Solar
Solar
17.5 MWWithdrawn / abandoned Merrimack, NHISO-NE Oct 2019target 2024
Gas project AF1-072, Kane County
Gas
17.2 MWWithdrawn / abandoned Kane, ILPJM Aug 2019target 2019
Seven Bridges Solar
Solar
17.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Mar 2019target 2025
W. Charlton substation - NG Western MA Area Cluster Study
Solar
17.0 MWWithdrawn / abandoned Worcester, MAISO-NE Mar 2019target 2022
Solar project AF1-004, Charles County
Solar
16.8 MWWithdrawn / abandoned Charles, MDPJM Apr 2019target 2021
Be-Astor
Solar
16.6 MWWithdrawn / abandoned Bedford, PAPJM Mar 2019target 2021
Onshore wind project AE2-244, Wayne County
Onshore wind
16.5 MWWithdrawn / abandoned Wayne, PAPJM Mar 2019target 2021
Onshore wind project AE2-243, Wayne County
Onshore wind
16.5 MWWithdrawn / abandoned Wayne, PAPJM Mar 2019target 2021
Kendall Combined Cycle increase
Gas
16.4 MWWithdrawn / abandoned Middlesex, MAISO-NE Apr 2019target 2025
Solar project AF1-131, Bedford County
Solar
16.2 MWWithdrawn / abandoned Bedford, PAPJM Sep 2019target 2021
FR-Boyer Mill 1
Solar
16.0 MWWithdrawn / abandoned Franklin, PAPJM Sep 2019target 2023
CL-Route 58 S
Solar
15.9 MWWithdrawn / abandoned Clarion, PAPJM Sep 2019target 2022
FR Boyer Mill 2
Solar
15.9 MWWithdrawn / abandoned Franklin, PAPJM Sep 2019target 2022
Ar-Pierce
Solar ยท AR-Pierce LLC
15.8 MWWithdrawn / abandoned Armstrong, PAPJM Sep 2019target 2022
Hosier Road Solar II
Solar
15.0 MWWithdrawn / abandoned City Of Suffolk, VAPJM Mar 2019target 2022
Solar
Solar
15.0 MWWithdrawn / abandoned Androscoggin, MEISO-NE Dec 2019target 2021
Gas project AF1-197, Allegheny County
Gas
15.0 MWWithdrawn / abandoned Allegheny, PAPJM Sep 2019target 2019
Solar project AE2-268, Middlesex County
Solar
15.0 MWWithdrawn / abandoned Middlesex, VAPJM Mar 2019target 2021
Solar project AF1-218, Somerset County
Solar
15.0 MWWithdrawn / abandoned Somerset, PAPJM Sep 2019target 2020
Palmyra Solar
Solar
15.0 MWWithdrawn / abandoned Lebanon, PAPJM Sep 2019target 2027
Solar project AF1-241, Adams County
Solar
15.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2019target 2022
Bluebell 3
Solar ยท Bluebell Solar
15.0 MWWithdrawn / abandoned ERCOT Aug 2019target 2020
Nellie Solar
Solar
15.0 MWWithdrawn / abandoned Sullivan, NHISO-NE Apr 2019target 2024
Crockett Solar Project
Solar
15.0 MWWithdrawn / abandoned Talbot, MDPJM Apr 2019target 2026
East Ridge Solar
Solar
15.0 MWWithdrawn / abandoned Lebanon, PAPJM Sep 2019target 2027
Bellegrove Solar
Solar
15.0 MWWithdrawn / abandoned Lebanon, PAPJM Sep 2019target 2027
Centre Hall
Solar
15.0 MWWithdrawn / abandoned Centre, PAPJM Sep 2019target 2026
Solar project AF1-095, Clearfield County
Solar
15.0 MWWithdrawn / abandoned Clearfield, PAPJM Aug 2019target 2023
Solar project 51, Polk County
Solar
14.9 MWWithdrawn / abandoned Polk, FLSoutheast Jan 2019target 2020
McAdoo repower
Onshore wind
14.7 MWWithdrawn / abandoned Dickens, TXERCOT Oct 2019
Millbury substation - NG Western MA Area Cluster Study
Solar
14.4 MWWithdrawn / abandoned Worcester, MAISO-NE Mar 2019target 2023
Battery Storage
Battery storage
14.0 MWWithdrawn / abandoned Kennebec, MEISO-NE Aug 2019target 2024
Battery storage project GEN-2019-076, Johnson County
Battery storage
14.0 MWWithdrawn / abandoned Johnson, NESPP May 2019target 2027
Sand Flat Road Solar Project
Solar
13.8 MWWithdrawn / abandoned Garrett, MDPJM Apr 2019target 2023
Solar project AF1-286, Bradford County
Solar
13.6 MWWithdrawn / abandoned Bradford, PAPJM Sep 2019target 2026
Solar project AF1-255, Bedford County
Solar
13.5 MWWithdrawn / abandoned Bedford, PAPJM Sep 2019target 2019
West Hampden 139 substation - NG Western MA Area Cluster Study
Solar
13.2 MWWithdrawn / abandoned Hampden, MAISO-NE Mar 2019target 2023
Onshore wind project GEN-2019-079, Gray County
Onshore wind
13.0 MWWithdrawn / abandoned Gray, KSSPP May 20192024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)