United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· ERCOT

McAdoo repower

McAdoo repower is a 14.7 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Dickens County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2019 (completed)
  2. Withdrawn / abandonedMar 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0295
Grid region
ERCOT (Texas)
Location
Dickens County, Texas
Technology
Wind: 14.7 MW
Total requested
14.7 MW
Queue status
Withdrawn
Entered queue
23 October 2019
Withdrawn
March 2020

Location

Marker shows the centre of Dickens County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Dickens County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem