πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

SOLAR Β· NYISO

Hornell Center 16

Hornell Center 16 is a 17.6 MW solar request withdrawn in the NYISO interconnection queue, in Allegany County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2019 (completed)
  2. Withdrawn / abandonedOct 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
888
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Sky Solar Inc.
Connection point (POI)
Moraine Substation 115kV
Location
Allegany County, New York
Technology
Solar: 17.6 MW
Total requested
17.6 MW
Queue status
Withdrawn
Entered queue
13 June 2019
Withdrawn
October 2019

Location

Marker shows the centre of Allegany County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Allegany County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem