United States › Grid › Interconnection queues › New York
BATTERY STORAGE · NYISOZenobe Burns LLC
Zenobe Burns LLC is a 100 MW battery storage request in interconnection study in the NYISO interconnection queue, in Allegany County, New York, connecting to NYSEG.
Queue statusIn planning
- PlanningQueued Sep 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- C24-238
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Zenobe Americas Inc.
- Connection point (POI)
- Moraine Rd 115kV Substation
- Location
- Allegany County, New York
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Queue status
- Active
- Entered queue
- 23 September 2024
- Proposed online date
- July 2028
Location
Marker shows the centre of Allegany County; the queue data does not give exact sites.
Other requests in Allegany County
- Moraine Solar Energy CenterSolar · 93.5 MW · in study
- Nine Mile Wind EnergyOnshore wind · 200 MW · withdrawn
- Nine Mile Wind FarmOnshore wind · 120 MW · withdrawn
- Sapphire SunSolar · 120 MW · withdrawn
- Cold Creek SolarSolar + storage · 120 MW · withdrawn
- Allegany WindOnshore wind · 100 MW · withdrawn
- Alfred Oaks SolarSolar + storage · 100 MW · withdrawn
- Zenobe Wellsville LLCBattery storage · 100 MW · withdrawn
- Moraine Solar Energy CenterSolar · 93.6 MW · withdrawn
- Cuba Wind ProjectOnshore wind · 86.5 MW · withdrawn
- Scio Solar FacilitySolar + storage · 50.0 MW · withdrawn
- Cuba Solar FacilitySolar + storage · 22.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem