United States › Grid › Interconnection queues › New York

SOLAR · NYISO

Moraine Solar Energy Center

Moraine Solar Energy Center is a 93.6 MW solar request withdrawn in the NYISO interconnection queue, in Allegany County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2024 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C24-027
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
EDF Renewables Development, Inc.
Connection point (POI)
115kV Moraine Road Substation
Location
Allegany County, New York
Technology
Solar: 93.6 MW
Total requested
93.6 MW
Queue status
Withdrawn
Entered queue
1 August 2024

Location

Marker shows the centre of Allegany County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Allegany County