United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
SOLAR Β· PJMSolar project AF1-218, Somerset County
Solar project AF1-218, Somerset County is a 15.0 MW solar request withdrawn in the PJM interconnection queue, in Somerset County, Pennsylvania, connecting to PENELEC.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2019 (completed)
- Withdrawn / abandonedOct 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF1-218
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PENELEC
- Connection point (POI)
- Scalp Level 23 kV
- Location
- Somerset County, Pennsylvania
- Technology
- Solar: 15.0 MW
- Total requested
- 15.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 27 September 2019
- Proposed online date
- December 2020
- Withdrawn
- October 2019
Location
Marker shows the centre of Somerset County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Somerset County
- Rockdale SolarSolar Β· 100 MW Β· agreement signed
- Solar project AH2-397, Somerset CountySolar Β· 200 MW Β· in study
- Solar project AH2-158, Somerset CountySolar Β· 80.0 MW Β· in study
- Julius SolarSolar Β· 66.0 MW Β· in study
- Solar project AG2-411, Somerset CountySolar Β· 63.0 MW Β· in study
- Solar project AI2-061, Somerset CountySolar Β· 17.6 MW Β· in study
- Solar project AH2-157, Somerset CountySolar Β· 12.0 MW Β· in study
- Solar project AH2-190, Somerset CountySolar Β· 12.0 MW Β· in study
- Solar project AI2-018, Somerset CountySolar Β· 4.0 MW Β· in study
- SunEast Hooversville SolarSolar Β· 20.0 MW Β· suspended
- SunEast Hooversville SolarSolar Β· 20.0 MW Β· suspended
- Stony Creek SolarSolar Β· 15.0 MW Β· suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem