πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

SOLAR Β· PJM

Solar project AF1-286, Bradford County

Solar project AF1-286, Bradford County is a 13.6 MW solar request withdrawn in the PJM interconnection queue, in Bradford County, Pennsylvania, connecting to PENELEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2019 (completed)
  2. Withdrawn / abandonedSep 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AF1-286
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
East Sayre 34.5 kV II
Location
Bradford County, Pennsylvania
Technology
Solar: 13.6 MW
Total requested
13.6 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Withdrawn
Entered queue
30 September 2019
Proposed online date
February 2026
Withdrawn
September 2023

Location

Marker shows the centre of Bradford County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Bradford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem