Gas project AI2-022, Bradford County

Gas project AI2-022, Bradford County is a 60.0 MW gas request in interconnection study in the PJM interconnection queue, in Bradford County, Pennsylvania, connecting to PENELEC.

Queue statusIn planning
  1. PlanningQueued Dec 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AI2-022
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
East Towanda 230 kV
Location
Bradford County, Pennsylvania
Technology
Gas: 60.0 MW
Total requested
60.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
20 December 2022
Proposed online date
May 2025

Location

Marker shows the centre of Bradford County; the queue data does not give exact sites.