United States βΊ Grid βΊ Interconnection queues βΊ New Hampshire
SOLAR Β· ISO-NENellie Solar
Nellie Solar is a 15.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Sullivan County, New Hampshire.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedOct 2024 (project stopped here)
- ConsentedJun 2022 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 868
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Eversource 34.5 kV line 3410 out of the North Road substation, extended along Maple Street, Newport NH.
- Location
- Sullivan County, New Hampshire
- Technology
- Solar: 15.0 MW
- Total requested
- 15.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed
- Queue status
- Withdrawn
- Entered queue
- 10 April 2019
- Agreement signed
- 21 June 2022
- Proposed online date
- October 2024
- Withdrawn
- October 2024
Location
Marker shows the centre of Sullivan County; the queue data does not give exact sites.
Power plants in New Hampshire Β· Transmission lines in New Hampshire
Other requests in Sullivan County
- Grissom SolarSolar Β· 5.0 MW Β· agreement signed
- LempsterOnshore wind Β· 24.0 MW Β· built
- Hemphill IncreaseOther Β· 3.4 MW Β· built
- SolarSolar Β· 46.5 MW Β· withdrawn
- Claremont SolarSolar Β· 20.0 MW Β· withdrawn
- SolarSolar Β· 19.8 MW Β· withdrawn
- SolarSolar Β· 10.0 MW Β· withdrawn
- Solar additionSolar Β· 10.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem