SOLAR Β· ISO-NE

Solar

Solar is a 10.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Sullivan County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2018 (completed)
  2. Withdrawn / abandonedMar 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
799
Grid region
ISO-NE (New England)
Connection point (POI)
Primary POI - PSNH 46 kV River Road substation; Alternate POI - GMP 46 kV Line 102
Location
Sullivan County, New Hampshire
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
16 November 2018
Proposed online date
November 2021
Withdrawn
March 2021

Location

Marker shows the centre of Sullivan County; the queue data does not give exact sites.

Power plants in New Hampshire Β· Transmission lines in New Hampshire

Other requests in Sullivan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem