🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Hampshire

ONSHORE WIND · ISO-NE

Lempster

Lempster is a 24.0 MW onshore wind request built and operating in the ISO-NE interconnection queue, in Sullivan County, New Hampshire, connecting to NU.

Queue statusOperating
  1. PlanningQueued Nov 2004 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Nov 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
127
Grid region
ISO-NE (New England)
Utility / transmission owner
NU
Connection point (POI)
PSNH 34.5 kV circuit from Newport Substation
Location
Sullivan County, New Hampshire
Technology
Wind: 24.0 MW
Total requested
24.0 MW
Service type
Other
Study phase
IA Executed
Queue status
Operational
Entered queue
15 November 2004
Proposed online date
November 2008

Location

Marker shows the centre of Sullivan County; the queue data does not give exact sites.

Power plants in New Hampshire · Transmission lines in New Hampshire

Other requests in Sullivan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem