Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,836452.0 GW
Active in queue452.0 GW1,836 requests
Agreement signed4,701 MW27 requests
Withdrawn47497.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,836 requests · page 25 of 37
ProjectCapacityStatusLocationRegionQueuedOnline
Great Hambino BESS
Battery storage · Atascosa BESS, LLC
123 MWIn study Atascosa, TXERCOT Sep 2025target 2027
Arnold Hills Storage
Battery storage · Arnold Hills Storage, LLC
123 MWIn study Henderson, TXERCOT Mar 2025target 2029
Solar project 790, Washington County
Solar
122 MWIn study Washington, IDWest Apr 2025target 2030
Iron Cowboy Solar
Solar + storage · Vaquero II Solar, LLC
121 MWIn study San Patricio, TXERCOT Jun 2025target 2028
Wagyu BESS SLF
Battery storage · Wagyu BESS, LLC
121 MWIn study Brazoria, TXERCOT Jun 2025target 2026
Borden Dino Solar
Solar + storage · Borden Dino Solar, LLC
121 MWIn study Borden, TXERCOT Apr 2025target 2028
Neal Battery
Solar + storage · CH Neal Battery LLC
121 MWIn study Wharton, TXERCOT Oct 2025target 2029
Buffalo Gap 1 Wind Repower
Onshore wind · Buffalo Gap Wind Farm, LLC
120 MWAgreement signed Nolan, TXERCOT Jan 2025target 2026
Dougherty County BESS
Battery storage
120 MWIn study Dougherty, GASoutheast Mar 2025
Solar project 282, Marion County
Solar
120 MWIn study Marion, SCSoutheast Jan 2025target 2030
Sawmill Junction
Solar
120 MWIn study Dodge, GASoutheast Mar 2025target 2029
Battery storage project J3930, Iberia Parish County
Battery storage
120 MWIn study Iberia Parish, LAMISO Feb 2025target 2029
Solar project GEN-2024-123, Shelby County
Solar
120 MWIn study Shelby, TXSPP Mar 2025target 2030
Onshore wind project J4096, Goodhue County
Onshore wind
120 MWIn study Goodhue, MNMISO Oct 2025target 2030
Solar project 25-IC-1324, Dodge County
Solar
120 MWIn study Dodge, GASoutheast Apr 2025target 2029
Solar project J2685, Sharkey County
Solar
120 MWIn study Sharkey, MSMISO Aug 2025target 2026
Solar project J4086, Wapello County
Solar
120 MWIn study Wapello, IAMISO Oct 2025target 2029
Solar project 25-IC-1373, Pike County
Solar
120 MWIn study Pike, GASoutheast Apr 2025target 2028
Onshore wind project GEN-2025-GR2, Roosevelt County
Onshore wind
120 MWIn study Roosevelt, NMSPP Jun 2025
Solar project AG2-516, Winnebago County
Solar · Kestrel Solar, LLC
120 MWIn study Winnebago, ILPJM Feb 2025target 2023
Solar + storage project GEN-2024-373, Choctaw County
Solar + storage
120 MWIn study Choctaw, OKSPP Mar 2025target 2029
Battery storage project GEN-2025-SR12, Noble County
Battery storage
116 MWIn study Noble, OKSPP May 2025target 2030
Amphion Solar Phase 3
Solar · Amphion Solar, LLC
115 MWIn study Atascosa, TXERCOT Apr 2025target 2029
Battery storage project GEN-2024-295, Eddy County
Battery storage
115 MWIn study Eddy, NMSPP Mar 2025target 2030
Battery storage project IA-PNM-2025-12, Cibola County
Battery storage
115 MWIn study Cibola, NMWest Mar 2025target 2027
Gas project 40603, Laramie County
Gas · Cheyenne Light, Fuel and Power Company
115 MWIn study Laramie, WYWest Aug 2025target 2028
Solar project AG2-583, Cumberland County
Solar · Boston Hill Solar, LLC
115 MWIn study Cumberland, VAPJM Jan 2025target 2026
Gas project 40969, Laramie County
Gas · Cheyenne Light, Fuel and Power Company
115 MWIn study Laramie, WYWest Aug 2025target 2028
Solar project J4142, Franklin Parish County
Solar
115 MWIn study Franklin Parish, LAMISO Oct 2025target 2030
Solar + storage project J4139, Nevada County
Solar + storage
115 MWIn study Nevada, ARMISO Sep 2025target 2030
Lost Pines Gas Recip Phase 2
Gas · LCRA
113 MWIn study Bastrop, TXERCOT Jul 2025target 2031
Schneider Gas Rice
Gas · LCRA
113 MWIn study Caldwell, TXERCOT Jul 2025target 2029
Lost Pines Gas Recip
Gas · LCRA
113 MWIn study Bastrop, TXERCOT Jul 2025target 2029
Schneider Gas Rice Phase 2
Gas · LCRA
113 MWIn study Caldwell, TXERCOT Jul 2025target 2031
Solar project AG2-441, Charlotte County
Solar · Virginia Electric and Power Company
113 MWIn study Charlotte, VAPJM Apr 2025target 2024
Onshore wind project J4126, Lenawee County
Onshore wind
112 MWIn study Lenawee, MIMISO Sep 2025target 2030
Battery storage project GEN-2025-SR11, Noble County
Battery storage
112 MWIn study Noble, OKSPP May 2025target 2030
Coyote Ridge BESS
Battery storage · Grenergy USA
111 MWIn study Brown, TXERCOT Jan 2025target 2027
Gas project 25-IC-1321, Lee County
Gas
111 MWIn study Lee, ALSoutheast Apr 2025target 2029
Gas project 25-IC-1320B, Lee County
Gas
111 MWIn study Lee, GASoutheast Apr 2025target 2034
Gas project 25-IC-1318, Autauga County
Gas
111 MWIn study Autauga, ALSoutheast Apr 2025target 2031
Gas project 25-IC-1319, Autauga County
Gas
111 MWIn study Autauga, ALSoutheast Apr 2025target 2032
Onshore wind project G1074, Gilliam County
Onshore wind
111 MWIn study Gilliam, ORWest Feb 2025target 2027
Carpet Tech Solar One
Solar · CT Solar One
111 MWIn study Kent, TXERCOT Jul 2025target 2028
Green Camp Solar II
Solar + storage · Riverlake Energy, LLC
110 MWIn study Marion, OHPJM Feb 2025target 2025
Solar project AG2-618, Charles County
Solar · DESRI Tidewater Development, L.L.C.
110 MWIn study Charles, MDPJM Mar 2025target 2023
Solar + storage project GEN-2024-162, Dakota County
Solar + storage
110 MWIn study Dakota, NESPP Mar 2025target 2030
Solar + storage project GI-CS-2025-28, Prowers County
Solar + storage
110 MWIn study Prowers, COWest Oct 2025target 2030
6505 US Hwy 221
Solar
110 MWIn study Jefferson, GASoutheast Apr 2025target 2028
Solar + storage project AG2-524, Grundy County
Solar + storage · Hog Run Solar, LLC
110 MWIn study Grundy, ILPJM Mar 2025target 2023
Page 25 of 37

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)