United States › Grid › Interconnection queues › Nebraska

SOLAR + STORAGE · SPP

Solar + storage project GEN-2024-162, Dakota County

Solar + storage project GEN-2024-162, Dakota County is a 110 MW solar + storage request in interconnection study in the SPP interconnection queue, in Dakota County, Nebraska, connecting to NPPD.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-162
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
Twin Church 230 kV Substation
Location
Dakota County, Nebraska
Technology
Solar: 110 MW · Battery
Total requested
110 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
January 2030

Location

Marker shows the centre of Dakota County; the queue data does not give exact sites.

Power plants in Nebraska · Transmission lines in Nebraska

Other requests in Dakota County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem